Achievements During June 2008
- Westwood commissioning completed on the Westwood to Wycarbah Duplication.
- Commissioning of Stage 2 signalling from Broadlea to Carborough Downs on the Broadlea-Mallawa-Wotonga Duplication.
- Shareholding Ministers' approval received for Grantleigh to Tunnel Duplication.
- Shareholding Ministers' approval received for Vermont Spur and Balloon Loop.
Upcoming events
July - Wycarbah commissioning due for completion on the Westwood to Wycarbah Duplication.
- Mallawa signalling and duplication from Carborough Downs to Mallawa due to be commissioned on the Broadlea-Mallawa Duplication.
August - Isaac Plains signalling and duplication from Mallawa to Isaac Plains to be commissioned on the Broadlea-Mallawa-Wotonga Duplication.
- Commissioning of Harrow Passing Loop.
 |