Corinda to Darra Rail Upgrade

Last Updated: Thursday, 6 November 2008

Project Fast Facts

 

  • Start Date: 2008
  • End Date: 2010
  • Link to new Springfield line
  • Station upgrades: Oxley, Darra

spacer
spacer spacer spacer spacer spacer spacer

This project, along with three other SEQIPRAIL infrastructure projects, is being delivered by QR through a program alliance with the private sector. 

Partners in the alliance, known as the TrackStar Alliance, are QR, Thiess United Group (a joint venture between Thiess Pty Ltd and United Group Infrastructure), Connell Wagner and Maunsell Australia. 

The benefits of the alliance include a cooperative and flexible approach to the delivery of complex projects over time, building strong relationships with the private sector, and achieving considerable savings in time and cost to QR and the industry.