Project Fast Facts

 

  • Start Date: 2008
  • End Date: 2010
  • Link to new Springfield line
  • Station upgrades: Oxley, Darra

spacer
spacer spacer spacer spacer spacer spacer

 

The following represent the planned timeframes for this project:

  • Early works:   Oct 07 - mid 2008 
  • Construction:  mid 2008
  • End date:        2010

 

 

 

 