Helensvale to Robina Duplication

Construction Phase | What does this mean?

Helensvale to Robina Duplication

Last Updated: Thursday, 6 November 2008

Project Fast Facts

This project is constructing a second track from Helensvale to Robina.

  • Start Date: August 2006
  • End Date: August 2008
  • Track length: 16.6 km
  • Rail bridges: 8 new, 11 upgraded

spacer
spacer spacer spacer spacer spacer spacer

Key benefits from this project include: 

  • Create around 500 direct and indirect jobs  
  • Increased track capacity for train services to support future population growth in the region
  • Local road improvements.        

The planning for the Helensvale to Robina second rail line has involved the commissioning of a detailed Environmental and Planning Study to ensure all environmental, social, economic and cultural aspects of the project have been taken into consideration. 

 