Helensvale to Robina Duplication

Construction Phase | What does this mean?

Helensvale to Robina Duplication

Last Updated: Thursday, 6 November 2008

Project Fast Facts

This project is constructing a second track from Helensvale to Robina.

  • Start Date: August 2006
  • End Date: August 2008
  • Track length: 16.6 km
  • Rail bridges: 8 new, 11 upgraded

spacer
spacer spacer spacer spacer spacer spacer

  • Preliminary design completed
  • Draft Environmental and Planning Study completed 
  • Construction commenced in August 2006
  • New rail line planned to be in operation by August 2008
  • Three new peak Gold Coast services - June 2007; and two new services - March 2008       

Piling north of Robina Station - October 07