Salisbury to Kuraby Third Track

Completion | What does this mean?

Salisbury to Kuraby Third Track

Last Updated: Thursday, 6 November 2008

Project Fast Facts

Building a third track between Salisbury and Kuraby to carry express trains to and from the Gold Coast.

  • Start Date: June 2006
  • End Date: Febuary 2008
  • Track length: 9.5km
  • Station upgrades: 7 stations from Coopers Plains to Kuraby
  • Bridges: Stable Swamp Creek at Bulimba Creek, Rebuild Mains Road over-bridge near Sunnybank

spacer
spacer spacer spacer spacer spacer spacer

The timeframes for this project were:

  • Mains Road upgrade - June 2006 to Aug 2007
  • Civil and station works construction - Sept 2006 to Feb 2008
  • Track laying - June 2007 to October 2007
  • Three new services on Gold Coast line - June 2007; two new services - March 2008    