Project Fast Facts
|
|
||||||||||||||
| Construction start: | August 2007 |
| Construction complete: | 2010 |
| Varsity Lakes Station site remediation: | September 2007 - mid-2008 |
| Construct tunnel, Easthill Drive: | December 2007 - mid-2009 |
| Robina train station stabling yard: | March 2008 - mid-2009 |
| New station: | Mid-2008 - late 2009 |
| Tracklaying: | January 2009 - April 2009 |