Robina to Varsity Lakes Rail Extension

Construction Phase | What does this mean?

Robina to Varsity Lakes Rail Extension

Last Updated: Thursday, 6 November 2008

Project Fast Facts

This project involves constructing a railway line from Robina to Varsity Lakes. 

  • Start Date: August 2007
  • End Date: Late 2009
  • Track length: 4.1km
  • New tunnel: Under Easthill Drive
  • New station: Varsity Lakes
  • Bridges: Three - Investigator Dr, Robina Parkway and Scottsdale Dr

spacer
spacer spacer spacer spacer spacer spacer

Project Timeframes

Construction start:August 2007
Construction complete:2010
Varsity Lakes Station site remediation: September 2007 - mid-2008
Construct tunnel, Easthill Drive: December 2007 - mid-2009
Robina train station stabling yard:March 2008 - mid-2009
New station:Mid-2008 - late 2009
Tracklaying:January 2009 - April 2009

The new road over rail bridge at Robina Parkway opened to traffic in mid 2008

A new train stabling yard is being constructed at Robina station